Your new HQ is taking shape.
52 working days to handover.
Floor 3 civil works closed out. The acoustic baffles arrived from Nuwood and are being installed on the main collaboration zone. We're slightly ahead of plan on partitions but the chilled-water line had a small leak — fixed this morning.
- Floor 3 partitions: 100% closed · ready for finishes
- Acoustic baffles · main collab: install started, 30% in
- Chilled-water line repair · resolved 9:14 AM
- 4 phone booths arrived from Framery — staged for floor 4
The daily story of your project.
This used to live in a WhatsApp group. Now it lives here — chronological, searchable, beautiful. Every day, photos and a narrative from your Site PM by 5 PM IST.
Major milestone today: Floor 3 partitions are fully closed and the acoustic baffles started going up on the main collaboration zone. We're tracking ~3% ahead of plan this week.
The morning began with a small chilled-water line leak in the floor 3 ceiling void — caught early during the daily walk and resolved by 9:14 AM. No impact to today's schedule.
The Featherlite chairs you signed off on Tuesday have entered production. Lead time confirmed at 18 days, which puts first delivery on May 24 — comfortably ahead of the FF&E window.
Tomorrow we begin floor 3 ceiling grid and start the AV first-fix on the boardrooms. Crestron team arrives at 10 AM.
The working schedule.
Twenty-four weeks, every task, every dependency. The black line shows where we are today. Hover any bar for detail.
Civil & MEP finishing a week earlier than plan thanks to a 2nd shift on Floor 3. We're holding that buffer for finishes.
Crestron deliveries need to land May 18. We've placed the order; we'll know by Friday.
Partitions pulled forward by 4 days. Snagging window extended by 2 days. No impact to handover date.
Drawings & renders.
Every sheet. Every version. Every comment. The whole drawing set in one place — not 47 emails with PDFs.
Your future office — walk it now.
A live 3D twin synced to today's construction state. Toggle layers, scrub time, click hotspots to see today's site photo overlaid on the render. Opens at twindigital.iwpsglobal.com.
Updates every site visit. Material changes ripple through automatically.
Each hotspot pulls today's site photo into the twin view. Drag-to-orbit, scroll-to-zoom.
A magic link that opens this twin in read-only mode on any device. No account required.
A few decisions from you.
When iWPS needs your call on a finish, fabric or fitting — it shows up here. Swipe-style. No 12-page emails. Three minutes a week.
The full BOM. Every status.
From spec sheet to "installed on site". Every line item of your Bill of Materials — furniture, finishes, MEP, AV — tracked through 6 stages, with supplier, quantity, and live status.
Milestones & payments.
Every commercial event in your project — milestones, invoices, payments — woven together. No more chasing finance over WhatsApp.
| Date | Description | Type | Amount | Status |
|---|---|---|---|---|
| 12 Feb 2026 | Project kickoff fee (M1) | Milestone | ₹1,48,00,000 | Paid |
| 4 Mar 2026 | Discovery + concept (M2) | Milestone | ₹2,96,00,000 | Paid |
| 15 Apr 2026 | Acoustic upgrade · variation #1 | Variation | ₹18,00,000 | Approved |
| 22 Apr 2026 | Reception stone upgrade · variation #2 | Variation | ₹14,00,000 | Approved |
| 28 Apr 2026 | Working drawings (M3) | Milestone | ₹2,96,00,000 | Paid |
| 2 May 2026 | Civil & MEP complete (M4) | Milestone | ₹4,44,00,000 | Invoiced · due 22 May |
Every photo, ever.
324 photos across 12 weeks of build. Browse chronologically, filter by floor or milestone, download as a coffee-table book at the end.
Open questions, transparent.
Every clarification, every change request, every site condition that needs your team's call. Visible to everyone — so nothing falls through.
| # | Issue | Floor | Owner | Raised | Status |
|---|---|---|---|---|---|
| RFI-024 | Confirm power point locations · boardroom AV wall | Floor 5 | WPP IT | 4 May | With WPP · 2 days |
| RFI-023 | Veneer vs solid for spine wall — clarify | Floor 3 | iWPS Design | 3 May | With iWPS · 3 days |
| RFI-022 | Cable raceway under reception desk · added | GF | Closed | 1 May | Resolved |
| RFI-021 | Pantry water-line routing · agreed alt | Floor 3 | Closed | 28 Apr | Resolved |
| RFI-020 | Glass partition height · executive corner | Floor 5 | Closed | 25 Apr | Resolved |
Build a report in 30 seconds.
Every iWPS-generated report is research-backed and beautiful. Weekly digests go out automatically. You can also generate one on demand — for a board update, an investor call, or just because.
The project conversation.
Replace the WhatsApp group. All messages are threaded to a project, searchable by floor or material, never lost.
Team & visits.
Who's on the project — from iWPS, from WPP, from our partner suppliers. And every site visit scheduled or completed.
| Date | Who | Focus | Notes |
|---|---|---|---|
| 15 May 2026 · Fri 11 AM | Sarah + CFO | Civil & MEP signoff walkthrough | iWPS to host · plan walkaround + cost review |
| 22 May 2026 · Fri 10 AM | Sarah + 4 dept heads | Floor 3 finish review | Sample wall built · final approval |
| 4 May 2026 | Sarah + WPP exec team (5) | Progress walk · floors 3 & 4 | Completed · 22 photos in feed |
| 18 Apr 2026 | Sarah + CEO | Concept signoff · all floors | Completed · concept approved |